商要:根据中国东方电气集团公司在印度承建的一火电站总承包项目(2 x300MW)主厂房工程钢筋混凝土预制方桩地基
处理的实践经验,提出在超固结粘性土质条件下,钢筋混凝土预制方桩承载能力的估算值和对现有理论计算单桩的承载能
力时计算参数取值的调整方法。
关键词:超固结粘性土;钢筋混凝土预制方桩;承载能力
中图分类号: TU271. 1
文献标识码: B
文章编号: 1001- 9006( 2013)04- -0075-06
Determination and Analysis on Working Load of Reinforced
Concrete Precast Pile in Over Consolidated Clay
LIANG Jian', XIE Baoan2
(1. Dongfang Eletric Corporation, Ld., 610036, Chengdu, China;
2. Northwest Electrie Power Design Instiute of China Power Engineeing Consuling ( Group),710000, Xian, China)
Abstract: With reference to the actual practice and experience derived from execution of an EPC contract for a thermal power plant in
India with installed capacity of 2 x 300MW, estimation of working load of reinforced concrete preeast pile in over consolidated elay and
modifcation to related coefficients in existing theoretical calculation for working load are presented.
Key words: over consolidated clay; reinforced concrete precast pile; working load
2004年7月,中国东方电气集团公司(以下简
土层越深,土质越坚硬。土壤力学性能指标属于
称DEC)通过国际招标方式取得了印度- -火电站总超固结硬质粉质粘土, 在整个厂区土质分布均匀,
承包项目的承包权。电站装机容量为2 x 300MW
土壤承载能力较高,地质条件好。DEC根据地质
燃煤机组(以下简称S工程)。
勘察报告的结果,结合国内同等建设规模及类似
按照DEC与印方签订的工程总承包合同的要
地质条件地基处理的成功经验,提出了S工程主厂
求,DEC 的地质勘察分包商于2004年11月完成了房 等建筑物地基采用天然地基的设计方案。
项目现场范围内所有建筑物的地质勘察工作。地
由于项目所在区域地处印度恒河流域形成的
质勘察结果表明:电站所在区域从地面开始,自
冲积平原,印方提出印度所有沿恒河流域(5km范
地面向下均为力学性能优良的硬质粉质粘土,且
围内)建成的大型火电站均采用桩基方案,并在合同